MN Holdings Bhd has secured a RM71.02 million contract from Tenaga Nasional Bhd (TNB) for the establishment of a new 132/33 kilovolt (kV) transmission main intake (PMU) in Blue Valley, Cameron Highlands, Pahang.
The group said its wholly owned subsidiary received the contract award from TNB on Aug 12, 2026. The project involves the establishment of a new 132/33kV PMU Blue Valley with a capacity of two 45 megavolt-amperes (MVA) transformers.
Under the contract, MNPT will undertake the supply, erection, installation, testing and commissioning of the new transmission intake, which will feature a double-busbar arrangement together with the necessary primary and secondary systems and associated civil works.
The contract is scheduled for completion within 900 days.
The company said the contract is not expected to have any immediate impact on its issued share capital or the shareholding structure of its substantial shareholders.