ECRL Project Half Way Completed, Operation Scheduled For January 2027

Construction of the East Coast Rail Link (ECRL) project has achieved 48.77 per cent progress, said Malaysia Rail Link Sdn Bhd (MRL) chairman Tan Sri Mohd Zuki Ali.

The Chief Secretary to the Government said the work progress is in line with the development of the project from Kota Bharu, Kelantan, to the Gombak Integrated Terminal, Selangor, which is scheduled for completion in December 2026 to enable the ECRL service to begin operation on January 2027.

“The encouraging rate of progress for this project is not only focused on infrastructure works and the construction of the mega project but also the involvement of local companies in the implementation of ECRL.

“This project involves the participation of about 2,700 local companies consisting of contractors, consultants and suppliers from 2017 to the first quarter of this year.

“The contract value involving the local companies in the ECRL project work has reached about RM12 billion, surpassing the target of RM10.8 billion for civil works in the project,” he said during the ECRL’s tunnel breakthrough at Kampung Gedung Siam 3 earlier today.

On the involvement of Bumiputera contractors, it involves a contract value of RM2.3 billion or 66 per cent of the target of RM3.5 billion for ECRL civil works.

Mohd Zuki said more than 21,000 workers were actively carrying out construction work on the national transport project at more than 1,600 work sites along the line.

On the tunnel construction in Kampung Gedung Siam 3, stretching 1.32 kilometres and scheduled for completion in April next year, 2024, the work progress went according to schedule.

The tunnel, with an average height of 13.47 metres and a width of 13.02 metres, needs to be built to allow the ECRL railway line to meet the maximum gradient of 0.74 per cent and to avoid open felling in the village area.

To date, the dredging works of 25 of the 40 tunnels in the ECRL construction have been carried out, including 21 tunnels in Section A (involving Kota Bharu – Dungun) and Section B (Dungun – Mentakab) and four in Section C (Mentakab – Port Klang), he added.

He said the installation of long-span bridges for five locations on the ECRL Section A and Section B has been fully implemented.

The ECRL project involves the construction of a new railway line spanning approximately 665 kilometres from Kota Bharu in Kelantan (on the East Coast) to the Klang Valley on the West Coast.

Previous articleAffin Bank Reports 2Q23 Net Profit Of RM113.23 Mil, Lower Than Last Year
Next articleMastercard, Binance To Terminate Crypto Card Programmes In Four Countries

LEAVE A REPLY

Please enter your comment!
Please enter your name here